PCP Installed in Multiphase Boosting Application

PCM provided a customer with a 120A24-HR pump, compliant with API 676, for use in a multiphase boosting application. 

The customer had a pad of oil wells that was located a significant distance from the processing facility. This resulted in a high back pressure in the flow line. These wells produce gas up the casing, which needs to be recombined with the liquids produced up the tubing to be sent to the processing facility. The high pressure in the flowline therefore limited the drawdown that was possible in the wells, and so production from the wells was reduced. By installing a progressing cavity pump equipped with PCM Slugger technology at the well pad, the customer has been able to reduce the back pressure on the wells from 15-20 bar down to 1 bar. 

This has both reduced stress on the downhole pumps in the wells and increased production by 7%.

PCP Installed in Multiphase Boosting Application

Challenge

The pad of wells was producing oil up the tubing and gas up the casing, both of which needed to be combined into the same flowline, which was operating at 15-20 bar, due to distance from the processing facility. 

Because the casing pressure cannot be lower than the flowline pressure, this meant that the flowing bottomhole pressure in the wells could not go below 15-20 bar, even if the pump submergence was minimized.  

Additionally, the higher pressure on the tubing side meant that the downhole pumps all required additional power to operate and were operating under a higher stress condition.  

The goal was to combine the gas and liquid together into the flow line with a pump and/or compressor to reduce the wellhead pressure. The presence of both viscous heavy oil and gas meant that many traditional pumps and compressors would not be possible. Also, the cost of a pump, compressor, and separator would be very high if the two streams were pressurized separately.

Results and Benefits

The pump has been operating at up to 100 m³/h, with free gas fraction up to 88%.

The intake pressure is roughly 1 bar, significantly lower than the flowline pressure (the pump discharge pressure) of 15-20 bar. In the three years that the pump has been installed, it has been running for a cumulative time of 1.5 years (the rest of the time, the bypass line is used).  The pump has not required any spare parts or major maintenance in this time and has shown no signs of reduced performance such as wear.

Furthermore, the flow rate from the wells on the pad has been less than predicted, due to wells being offline. The pump was designed for a higher flow rate, requiring an operating speed of 120-240 rpm, but the true operating speed has been in the range of 60-80 rpm, which is set automatically by the control system and VSD.  There has been no reduction in the pump’s performance due to operating at this lower speed. Despite this, the individual wells have been able to increase production by up to 7% over what they were able to produce at the higher wellhead pressure.

PCM’s solution Slugger technology

PCM’s solution for the customer was a single progressing cavity pump, which can handle heavy oil and gas, even if solids and water are also present. The PCM Slugger technology was chosen due the possibility of a high gas fraction at the pump intake when the upstream pressure was reduced. While PCPs can pump gas, the run life may be reduced due to a non-linear pressure gradient inside the pump. The hydraulic regulators inherent in the PCM Slugger technology linearize the pressure gradient, allowing good run-life at up to 90% gas volume fraction at the pump intake.

A PCP is a positive displacement pump, which means that the flow rate is proportional to the pump speed. However, in this case, the flow rate coming into the pump would be variable as some of the wells on the pad go offline or come back online, or as the individual wells’ productivity changes. Therefore, PCM designed a customized control system using a variable speed drive (VSD) to change the pump speed according to the available flow rate from the wells at any given time.

To ensure that no leakage of oil to the environment would be possible, an API Plan 53B seal system was included with the pump. Despite the presence of a lubricating barrier fluid, there was a concern that the high gas fraction at the pump intake may have a negative effect on the shaft seals. Therefore, the pump was configured with the shaft at the discharge end of the pump. The seals operate at the discharge pressure, but the gas volume fraction is much smaller due to the higher pressure.

A pressure relief valve was included to redirect flow from the pump discharge to the intake in the event of a blockage in the flowline. A bypass line was also included so that the wells could still operate when the pump is shut off, either for maintenance, or because it is not needed.

 

Discover
PCM SLUGGER HRPCP